top of page

BIV - NEW CONSTRUCTION OF A PHARMACEUTICAL PRODUCTION PLANT IN VIETNAM

New construction of a building complex for the production and storage of pharmaceutical products as well as their laboratory analysis using reinforced concrete skeleton construction. This includes

Laboratory areas with chemical, biochemical and serological laboratories, microbiology laboratory area, PCR laboratories (cleanliness class D), sterile area (cleanliness class B), storage, technical and production rooms, cold storage rooms, sanitary rooms. The planning was carried out in compliance with local fire protection regulations.

SCOPE OF SERVICES

Object planning LP 1 – 3

Structural engineering LP 1 – 3

Outdoor facilities planning LP 1 – 3

Functional specification

COST

KG 300: 17 million euros
KG 400: 12 million euros

AREA

20 830 m² GFA

PROJECT PERIOD

2016 - 2017

consultants. architects. engineers.