H43 - RENOVATION, RENOVATION AND REORGANISATION OF THE INSTITUTE FOR PATHOLOGY AT HOUSE 43, UNIVERSITY HOSPITAL CARL G. CARUS DRESDEN

The building, which was constructed in 1964 as the Pathological Institute, has been partially restructured.

The laboratory areas in the basement, ground floor, first and second floors have been functionally reorganized. This included the comprehensive renovation, reorganization and re-equipment of the laboratory areas including equipment, installations, structural elements and surfaces.

60% of the laboratory rooms have received new laboratory equipment.

The measures were carried out while maintaining the institute's functions and included a complete gutting and reconstruction.

SCOPE OF SERVICES

Preliminary Design

Basic Engineering Design

Permit Design

Detailed Engineering Design

Tendering & Procurement

Site Supervision

COST

1 million euros

AREA

1700 m² GFA

PROJECT PERIOD

2009 - 2010